Back to customer stories

Superb sequencing at New Fetter Lane, a new 15-storey office project enables rapid sale for Mace

Asta Powerproject®
Customer = PP Fetter Lane Mace Credit © KS Photography 056 18.11.15

12-14 New Fetter Lane, a 15-storey office building on the western edge of the City of London, was a project that almost did not happen. After its original planning in 2007 was delayed, first by the recession and then right-of-light issues, it was finally redesigned and commenced in Spring 2013, with project completion achieved in November 2015. James Williams, a new recruit at Mace at the time, certainly had a challenging first project for the company. Superb planning, sequencing and logistics were an absolute essential. The team had an ambitious programme to deliver, which required extremely careful planning to meet tight budget and timing requirements alike. Mace utilised Asta Powerproject, its standard planning and project management software, for the purpose. Senior Planning Manager, Barry Hancock, told us:

“This project required a lot of testing to try out different ideas. We use Asta Powerproject first to set up contract and delivery programmes, and structure them so that we can easily put things in and take them out, in order to explore different scenarios.”

Using the software helped the team to explore and plan ideas that would enable smoother progress and even accelerate certain critical milestones, such as getting the building weatherproof; to this end, Project Manager James Williams re-sited a crane originally to be situated in the boiler room, moving it to a concrete cap on top of one of the low-rise lifts. This also accelerated progress on the mechanical, electrical and plumbing. The project featured many innovative ideas, including re-planning how cladding panels were to be installed: instead of bringing them up the exterior of the building, above the busy pedestrian walkways of the City, with associated safety risks, they were instead brought up through the floors, distributed via a hoist, and finally positioned using a spider crane on the floor above. It meant frequent re-planning:

“This project was more intense than usual in terms of our use of Asta Powerproject. By the end the programme was very large, somewhere between 8000 and 9000 activities. We went into a huge amount of detail about the commissioning, and again to help us manage the close-out process – that was good, because we were able to manage the process better”

explained Barry. As an experienced Asta Powerproject user for over 25 years, Barry was able to use the software easily to resolve issues. He said:

“The way we work is for the Project Manager, myself and the other team members to sit down regularly, sometimes with sub-contractors if necessary, and explore each issue. We try out different scenarios in Asta Powerproject, to see ‘what if’ something happens and what would help the programme. We can use it to show clients what we had originally versus their changes, so that we can apply for an extension of time if we need it.”

Managing progress on this complex site in a hugely busy part of the City of London was a challenge, and Barry has since moved on to deploy Asta SiteProgress, the mobile site progress companion to Asta Powerproject software, at a subsequent City development. In explaining why it would be useful, Barry outlined that:

It will be exceedingly useful to help us try to keep everything under constant control, and should improve things a lot. Planners go around sites all the time, checking all updates we have received, and verifying what we have been told. We really need a way to speed that up! If I can punch progress updates into the app and then upload it to the programme, it’s going to be a lot better.”

The team’s efforts certainly paid off in the end. Not only was the delivery of this project hailed as a triumph, James Williams received a Construction Manager of the Year Award as a result, and praised the whole-team effort that had led to the project’s success. The client was delighted too – and was even able to sell on the building before the construction phase had completed.

The power behind successful projects: book a free demo to experience Asta Powerproject by Elecosoft.

Image credit © KS Photography 056 18.11.15

Related customer stories

McGee uses Asta Powerproject to make the ‘impossible’ Mayfair Hotel Megabuild a reality
Specialist Engineering Contractor, McGee, used Asta Powerproject to sequence and manage a ground-breaking five-storey mega basement for Claridge’s Hotel. Our cutting-edge planning and project management...
Read more
Asta Powerproject®
Asta Powerproject ensures Taunton Diagnostics Centre is future-fit
The Kier Group used Asta Powerproject planning and project management software to orchestrate the complex fit-out of a new diagnostics centre in Somerset, UK. Asta...
Read more
Asta Powerproject®