Do you have a record of the original programme dates?

Do you have a record of the original programme dates?

Creating a baseline in Asta Powerproject will protect your original contract dates. You cannot move or progress baseline tasks, so they are an ideal reference to how the project looked prior to any work being carried out. You can also tell your spreadsheet columns to display baseline information.