Do you have a record of the original programme dates?
-
Help guides
-
- Can you tell the difference between bars and tasks?
- Do you know how to identify part-critical tasks?
- Can you plan your future projects faster with task pools?
- Do you display alternate shading and default task display?
- Are you using multiple cost centres and need to identify individual costs in the table?
- Do you want to highlight or ignore specific links?
- Is your heirarchy difficult to understand?
- Do you need to show spreadsheet information for a particular code?
- Do you need to track your logic through the programme?
- Is your Project View panel looking cluttered?
- Does one of your team need to take a holiday?
- Do you need more than one Notes column?
- Having difficulties visualising logic links?
- Do you have a record of the original programme dates?
- What it is happening in your project for the next 6 weeks?
- Do you need to calculate cost per time unit?
- What is the difference between Slip and Variance?
- Can you make your summaries reflect tasks that pass a filter?
- Do you need to calculate durations and progress based on task work?
- Want to save a pre-set of spreadsheet columns?
- Booking out sections of the programme to other planners
- Adding shading that moves automatically with variable dates
- Did you know that you can put multiple tasks on the same line?
- Do you know how to track your resource allocations?
- Introduction to Templates
- Do you need to change your project calendar
-
Do you have a record of the original programme dates?
Creating a baseline in Asta Powerproject will protect your original contract dates. You cannot move or progress baseline tasks, so they are an ideal reference to how the project looked prior to any work being carried out. You can also tell your spreadsheet columns to display baseline information.